12

某淤泥地基打设排水板后采用堆载预压处理,堆载至 2020 年 7月 16 日后,某原地表测点的实测沉降值见下表。现用双曲线法预测后期沉降,使用线性函数回归的tt0StS0\cfrac{t-t_0}{S_t - S_0}(tt0)(t-t_0) 关系曲线见下图。计算 2020 年 12 月 31 日该位置处的固结度最接近下列哪个选项?(S0S_0t=t0t=t_0时间对应的初期沉降量,StS_t后为任意 1 时间对应的派降量,t0t_0为所选取初始沉降对应时间。)

沉降观测日期累计沉降量(mm)tt0(m)t - t_0(m)StS0(mm)S_t - S_0(mm)(tt0)/(StS0)(d/mm)(t-t_0)/(S_t-S_0)(d/mm)
2020-7-16512.600/
2020-9-241336.970824.30.0849
2020-10-31352.179839.60.0941
2020-10-61359.382846.80.0968
2020-10-91364.585851.90.0998
2020-10-121368.188855.50.1029
2020-10-151371.491858.80.1060
2020-10-181374.494861.80.1091
2020-10-241378.1100865.50.1155
2020-10-271380.1103867.50.1187
2020-10-301382.7106870.10.1218
2020-12-31?168//

(A) 80%

(B) 85%

(C) 90%

(D) 95%

解答
tt0StS0=0.001×168+0.0127=0.1807 StS0=168/0.1807=929.72 St=929.72+512.6=1442.32mm tt0StS0=0.001×(tt0)=0.01271StS0=0.001+0.0127tt0 t=1SS0=0.001S=1000+512.6=1512.6mm Ut=1442.3/1512.6=0.954\cfrac{t-t_0}{S_t - S_0} = 0.001 × 168 + 0.0127 = 0.1807 \\~\\ S_t - S_0 = 168 / 0.1807 = 929.72 \\~\\ S_t = 929.72 + 512.6 = 1442.32 mm \\~\\ \cfrac{t-t_0}{S_t - S_0} = 0.001 × (t - t_0) = 0.0127 \Rarr \cfrac{1}{S_t - S_0} = 0.001 + \cfrac{0.0127}{t-t_0} \\~\\ t = \infin \Rarr \cfrac{1}{S_{\infin} - S_0} = 0.001 \Rarr S_{\infin} = 1000 + 512.6 = 1512.6mm \\~\\ U_t = 1442.3/ 1512.6 = 0.954

选D